Which is a purpose of measuring Key Performance Indicators for a P3O?

The correct answer is A. Demonstrate a P3O's successes to the organization. See the full explanation below for the reasoning.

Question

Which is a purpose of measuring Key Performance Indicators for a P3O?

Options

  • ADemonstrate a P3O's successes to the organization
  • BDetermine project progress against its plan
  • CIdentify the resources required within a P3O
  • DIdentify areas of personal improvement for Project Managers

How the community answered

(35 responses)
  • A
    86% (30)
  • B
    9% (3)
  • C
    3% (1)
  • D
    3% (1)