EXIN
P3OF · Question #39
Which of the following actions are recommended when implementing a P3O model with Hub Portfolio Offices? 1. Appoint a P3O Sponsor to act as Senior Responsible Owner 2. Allow temporary offices to…
The correct answer is C. 1, 3, 4. See the full explanation below for the reasoning.
Question
Which of the following actions are recommended when implementing a P3O model with Hub Portfolio Offices? 1. Appoint a P3O Sponsor to act as Senior Responsible Owner 2. Allow temporary offices to define their own standards and processes 3. Run the implementation as a programme with appropriate governance 4. Use appropriate programme management lifecycles and processes
Options
- A1, 2, 3
- B1, 2, 4
- C1, 3, 4
- D2, 3, 4
How the community answered
(29 responses)- A10% (3)
- B3% (1)
- C79% (23)
- D7% (2)
Community Discussion