Which office within a P3O model provides delivery support to the 'Identify' process of a programme?

The correct answer is B. Organization Portfolio Office. See the full explanation below for the reasoning.

Question

Which office within a P3O model provides delivery support to the 'Identify' process of a programme?

Options

  • ATemporary Project Office
  • BOrganization Portfolio Office
  • CCOE
  • DTemporary Programme Office

How the community answered

(37 responses)
  • A
    8% (3)
  • B
    76% (28)
  • C
    14% (5)
  • D
    3% (1)

Community Discussion