EXIN
P3OF · Question #29
Which office within a P3O model provides delivery support to the 'Identify' process of a programme?
The correct answer is B. Organization Portfolio Office. See the full explanation below for the reasoning.
Question
Which office within a P3O model provides delivery support to the 'Identify' process of a programme?
Options
- ATemporary Project Office
- BOrganization Portfolio Office
- CCOE
- DTemporary Programme Office
How the community answered
(37 responses)- A8% (3)
- B76% (28)
- C14% (5)
- D3% (1)
Community Discussion