P3OF · Question #149

Why do senior managers need to agree on which PPM problems they rate as critical?

The correct answer is B. Allows the P3O Sponsor to gain consensus on a common P3O vision. See the full explanation below for the reasoning.

Question

Why do senior managers need to agree on which PPM problems they rate as critical?

Options

  • ADefines a portfolio prioritization and optimization technique
  • BAllows the P3O Sponsor to gain consensus on a common P3O vision
  • CJustifies to senior management the investment in a P3O
  • DDefines the lifecycle for implementing a permanent P3O

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    78% (18)
  • C
    13% (3)
  • D
    4% (1)