EXIN
P3OF · Question #123
Which activity should take place when recycling capability within a temporary Programme Office lifecycle?
The correct answer is C. Feedback to the COE any methods used as part of programme delivery. See the full explanation below for the reasoning.
Question
Which activity should take place when recycling capability within a temporary Programme Office lifecycle?
Options
- ATransfer resources back to operational areas
- BReview processes to ensure they continue to support a programme
- CFeedback to the COE any methods used as part of programme delivery
- DReturn office accommodation back to business as usual
How the community answered
(22 responses)- A14% (3)
- B5% (1)
- C77% (17)
- D5% (1)
Community Discussion