What resource commitments should be taken into account as part of portfolio management?
The correct answer is D. Programme, project and business as usual. See the full explanation below for the reasoning.
Question
What resource commitments should be taken into account as part of portfolio management?
Options
- AProgramme only
- BProgramme and project only
- CProgramme and business as usual only
- DProgramme, project and business as usual
How the community answered
(56 responses)- A4% (2)
- B14% (8)
- C7% (4)
- D75% (42)