According to the IBM PureApplicationTM System whiteboard, what is the average percentage of IT budget spent on maintenance and operation costs?

The correct answer is C. 70%. See the full explanation below for the reasoning.

Question

According to the IBM PureApplicationTM System whiteboard, what is the average percentage of IT budget spent on maintenance and operation costs?

Options

  • A50%
  • B95%
  • C70%
  • D35%

How the community answered

(45 responses)
  • A
    13% (6)
  • B
    7% (3)
  • C
    76% (34)
  • D
    4% (2)