OGEA-101 · Question #91

What are the following activities part of? - Initial risk assessment - Risk mitigation and residual risk assessment - Risk monitoring

The correct answer is A. Risk Management. The following activities are part of Risk Management: - Initial risk assessment - Risk mitigation and residual risk assessment - Risk monitoring Risk Management is the process of identifying, assessing, and responding to risks that may affect the achievement of the enterprise's…

Architecture Governance

Question

What are the following activities part of?

  • Initial risk assessment
  • Risk mitigation and residual risk assessment
  • Risk monitoring

Options

  • ARisk Management
  • BPhase A
  • CSecurity Architecture
  • DPhase C

How the community answered

(34 responses)
  • A
    88% (30)
  • B
    3% (1)
  • C
    6% (2)
  • D
    3% (1)

Explanation

The following activities are part of Risk Management: - Initial risk assessment - Risk mitigation and residual risk assessment - Risk monitoring Risk Management is the process of identifying, assessing, and responding to risks that may affect the achievement of the enterprise's objectives. Risk Management involves balancing positive and negative outcomes resulting from the realization of either opportunities or threats.

Topics

#risk management#risk assessment#risk mitigation#risk monitoring