OGEA-101 · Question #81
Consider the following statement: According to the TOGAF Standard a governed approach of a particular deliverable will ensure a system of continuous monitoring to check integrity changes…
The correct answer is A. An Architecture Contract. An Architecture Contract is a deliverable that specifies the responsibilities and obligations of the parties involved in the implementation and governance of an architecture. It ensures a system of continuous monitoring to check integrity changes decision-making and audit of…
Question
Consider the following statement:
According to the TOGAF Standard a governed approach of a particular deliverable will ensure a system of continuous monitoring to check integrity changes decision-making and audit of all architecture-related activities Which deliverable is being referred to?
Options
- AAn Architecture Contract
- BThe Architecture Definition Document
- CThe Architecture Vision
- DThe Statement of Architecture Work
How the community answered
(28 responses)- A75% (21)
- B7% (2)
- C4% (1)
- D14% (4)
Explanation
An Architecture Contract is a deliverable that specifies the responsibilities and obligations of the parties involved in the implementation and governance of an architecture. It ensures a system of continuous monitoring to check integrity changes decision-making and audit of all architecture- related activities.