Consider the following statement: According to the TOGAF Standard a governed approach of a particular deliverable will ensure a system of continuous monitoring to check integrity changes…

The correct answer is A. An Architecture Contract. An Architecture Contract is a deliverable that specifies the responsibilities and obligations of the parties involved in the implementation and governance of an architecture. It ensures a system of continuous monitoring to check integrity changes decision-making and audit of…

Architecture Governance

Question

Consider the following statement:

According to the TOGAF Standard a governed approach of a particular deliverable will ensure a system of continuous monitoring to check integrity changes decision-making and audit of all architecture-related activities Which deliverable is being referred to?

Options

  • AAn Architecture Contract
  • BThe Architecture Definition Document
  • CThe Architecture Vision
  • DThe Statement of Architecture Work

How the community answered

(28 responses)
  • A
    75% (21)
  • B
    7% (2)
  • C
    4% (1)
  • D
    14% (4)

Explanation

An Architecture Contract is a deliverable that specifies the responsibilities and obligations of the parties involved in the implementation and governance of an architecture. It ensures a system of continuous monitoring to check integrity changes decision-making and audit of all architecture- related activities.

Topics

#Architecture Contract#governance monitoring#audit#key deliverables