OG0-093 · Question #348
Scenario Please read this scenario prior to answering the Question You are serving as the Lead Architect for an Enterprise Architecture project team within a multinational oil and gas corporation…
The correct answer is B. You recommend that an analysis of the stakeholders is undertaken, including development of a. Given the complexity of a multinational corporation with varied operations, safety priorities, and regulatory requirements, identifying and analyzing stakeholders is the most critical initial step.
Question
Scenario Please read this scenario prior to answering the Question You are serving as the Lead Architect for an Enterprise Architecture project team within a multinational oil and gas corporation. It is organized into two major business groupings:
-Upstream operations which include exploration for crude oil and natural gas and operating the infrastructure necessary to deliver oil and gas to the market -Downstream operations which include the manufacturing, distribution and marketing activities for oil products and chemicals Safety is a priority for the company, with the aim to ensure it causes zero harm to people and the environment. The company has to satisfy the regulatory requirements of each of the countries it operates in. The downstream business generates a third of the company's profits worldwide and includes more than 30,000 petrol stations and various oil refineries. In some countries it also includes oil refining, a retail petrol station network, lubricants manufacture and marketing, industrial fuel and lubricants sales. The practice for the downstream business has been to operate locally, managed by local "operating companies". The Governing Board is concerned about the risk posed by operating in this complex global environment with a large part of the downstream business represented by local operating companies. As a result, the Chief Executive Officer (CEO) has appointed a Chief Compliance Officer (CCO) to be responsible for overseeing and managing compliance issues for the corporation. The CCO reports directly to the CEO. The CCO has approved the expenditure of resources to establish an Enterprise Architecture program, and has mandated the use of the TOGAF standard as the framework. He has requested to be informed about the status of downstream operations that could impact regulatory compliance. He also wants the corporate legal staff and auditors to analyze all proposed new downstream operations to ensure that they are within the legal guidelines for each country. In addition, the local operating companies should be able to see that the architecture is appropriate for their needs. The architecture project team has worked with the sponsor to complete a detailed Request for Architecture Work providing the high level project description. As the project commences the next phase, the necessary approvals from corporate and line management have been received. Refer to the Scenario You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Chief Compliance Officer, legal staff, auditors and the local operating companies. Based on the TOGAF standard, Version 9.2, which of the following is the best answer?
Options
- AYou recommend that a set of models be created for each project architecture that can be used to
- BYou recommend that an analysis of the stakeholders is undertaken, including development of a
- CYou recommend that the ArchiMate modeling language is used to create a set of models that can
- DYou recommend that a Communications Plan be created to address the powerful and influential
How the community answered
(20 responses)- A5% (1)
- B80% (16)
- C5% (1)
- D10% (2)
Why each option
Given the complexity of a multinational corporation with varied operations, safety priorities, and regulatory requirements, identifying and analyzing stakeholders is the most critical initial step.
Creating models is a subsequent step after understanding stakeholder needs and the architectural vision, which are shaped by stakeholder analysis.
In the TOGAF ADM, particularly in the Preliminary Phase and Phase A (Architecture Vision), performing a thorough stakeholder analysis is fundamental. Understanding the diverse concerns, objectives, and influence of all stakeholders, including those related to safety and regulatory bodies, is essential for defining a relevant architecture vision and ensuring project success and acceptance.
While ArchiMate is a useful modeling language, the choice of tools follows the identification of stakeholder requirements and the overall architectural approach.
A Communications Plan is important, but it is developed based on the insights gained from an initial stakeholder analysis, making analysis a prerequisite.
Concept tested: TOGAF ADM - Stakeholder Management
Source: https://pubs.opengroup.org/architecture/togaf10-doc/arch/chap23.html#_Stakeholder_Management
Topics
Community Discussion
No community discussion yet for this question.