Which phase of the ADM focuses on the governance and management of the Architecture Contracts that cover the overall implementation and deployment process?

The correct answer is D. Phase G. This question asks which phase of the Architecture Development Method (ADM) specifically focuses on the governance and management of Architecture Contracts during implementation.

ADM Phase G: Implementation Governance

Question

Which phase of the ADM focuses on the governance and management of the Architecture Contracts that cover the overall implementation and deployment process?

Options

  • ARequirements Management
  • BPhase E
  • CPhase F
  • DPhase G
  • EPhase H

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    3% (1)
  • D
    89% (31)
  • E
    3% (1)

Why each option

This question asks which phase of the Architecture Development Method (ADM) specifically focuses on the governance and management of Architecture Contracts during implementation.

ARequirements Management

Requirements Management is an ongoing process throughout the ADM, not a distinct phase focused on implementation governance of contracts.

BPhase E

Phase E, Opportunities & Solutions, focuses on identifying delivery vehicles and creating an initial implementation plan, not on the governance of implementation contracts.

CPhase F

Phase F, Migration Planning, focuses on creating detailed implementation and migration plans, not the ongoing governance during implementation.

DPhase GCorrect

Phase G, Implementation Governance, is the ADM phase that focuses on providing architectural oversight of the implementation and deployment projects. This includes ensuring compliance with the defined architecture and managing the Architecture Contracts which guide the overall implementation process.

EPhase H

Phase H, Architecture Change Management, focuses on managing changes to the deployed architecture, not the governance of initial implementation contracts.

Concept tested: TOGAF ADM Phase G - Implementation Governance

Source: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap8.html