nerdexam
The_Open_Group

OG0-093 · Question #129

Complete the sentence. According to TOGAF, an objective of Phase G, Implementation Governance, is to______________.

The correct answer is C. ensure conformance with the defined architecture by the implementation projects. Phase G, Implementation Governance, in TOGAF aims to oversee implementation projects, ensuring they conform to the defined architecture.

ADM Phase G: Implementation Governance

Question

Complete the sentence. According to TOGAF, an objective of Phase G, Implementation Governance, is to______________.

Options

  • Aassess the performance of the architecture and make recommendations for change
  • Bensure the baseline architecture continues to be fit-for-purpose
  • Censure conformance with the defined architecture by the implementation projects
  • Destablish an architecture change management process for the architecture finalized in the
  • Eoperate the governance framework

How the community answered

(22 responses)
  • B
    5% (1)
  • C
    91% (20)
  • D
    5% (1)

Why each option

Phase G, Implementation Governance, in TOGAF aims to oversee implementation projects, ensuring they conform to the defined architecture.

Aassess the performance of the architecture and make recommendations for change

Assessing architecture performance and recommending changes is an activity typically associated with Phase H, Architecture Change Management.

Bensure the baseline architecture continues to be fit-for-purpose

Ensuring the baseline architecture remains fit-for-purpose is a continuous governance activity, but not the specific objective of Phase G, which focuses on project implementation conformance.

Censure conformance with the defined architecture by the implementation projectsCorrect

Phase G's primary objective is to ensure that the architecture developed in previous phases is correctly implemented by various projects, thus maintaining architectural integrity and conformance throughout the development lifecycle. This involves monitoring projects and providing architectural guidance to ensure adherence to standards and designs.

Destablish an architecture change management process for the architecture finalized in the

Establishing an architecture change management process is a key activity within Phase H, Architecture Change Management.

Eoperate the governance framework

Operating the governance framework is a broader ongoing activity, not the specific, core objective of the implementation-focused Phase G.

Concept tested: TOGAF ADM Phase G objectives

Source: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap07.html#tag_07_08_02

Topics

#Implementation Governance#ADM Phase G#architecture conformance

Community Discussion

No community discussion yet for this question.

Full OG0-093 Practice