OG0-093 · Question #166
In Phases B, C, and D of the ADIVI cycle the first step defined is to select reference models, viewpoints, and tools. Which of the following is the next step in each of these phases?
The correct answer is C. Develop Baseline Architecture. This question asks for the second step common to Phases B, C, and D of the TOGAF ADM cycle, following the selection of reference models, viewpoints, and tools.
Question
In Phases B, C, and D of the ADIVI cycle the first step defined is to select reference models, viewpoints, and tools. Which of the following is the next step in each of these phases?
Options
- AConduct formal stakeholder review
- BCreate Architecture Definition Document
- CDevelop Baseline Architecture
- DPerform gap analysis
- EResolve impacts across the Architecture Landscape
How the community answered
(55 responses)- B4% (2)
- C91% (50)
- D4% (2)
- E2% (1)
Why each option
This question asks for the second step common to Phases B, C, and D of the TOGAF ADM cycle, following the selection of reference models, viewpoints, and tools.
Conducting a formal stakeholder review typically occurs later in these phases, often after defining the Target Architecture and performing gap analysis.
Creating the Architecture Definition Document is usually an output or an activity towards the end of these phases, compiling the architecture work.
In Phases B (Business Architecture), C (Information Systems Architectures), and D (Technology Architecture) of the TOGAF ADM, after selecting reference models, viewpoints, and tools, the next common step is to "Develop Baseline Architecture." This involves describing the 'as-is' state of the relevant architectural domain before defining the target state.
Performing gap analysis happens after both Baseline and Target Architectures are developed, to identify differences between them.
Resolving impacts across the Architecture Landscape is a broader activity that spans multiple phases and is not the immediate next step after selecting tools.
Concept tested: TOGAF ADM Phases B, C, D common steps
Source: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap05.html