Complete the sentence. A gap analysis will enable the architect to do all of the following except _____.

The correct answer is E. identify potential vendors to provide new building blocks. Gap analysis is a TOGAF technique used to compare the Baseline Architecture with the Target Architecture to identify differences - what was intentionally eliminated, what is carried over, what is inadvertently omitted, and what new building blocks are needed. However, identifying

Submitted by lukas.cz· Apr 18, 2026ADM Guidelines and Techniques

Question

Complete the sentence. A gap analysis will enable the architect to do all of the following except _____.

Options

  • Aidentify building blocks that have been inadvertently omitted
  • Bidentify building blocks that have been intentionally eliminated
  • Cidentify building blocks to be carried over
  • Didentify new building blocks that are needed
  • Eidentify potential vendors to provide new building blocks

How the community answered

(58 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    3% (2)
  • E
    93% (54)

Explanation

Gap analysis is a TOGAF technique used to compare the Baseline Architecture with the Target Architecture to identify differences - what was intentionally eliminated, what is carried over, what is inadvertently omitted, and what new building blocks are needed. However, identifying potential vendors to provide new building blocks is not a purpose of gap analysis. Vendor selection is a procurement or sourcing activity that occurs separately (often in Phase E or later). Gap analysis is strictly about architectural completeness and change identification, not market or vendor evaluation.

Topics

#Gap Analysis#Building Blocks#ADM Techniques#Architecture Planning