OG0-091 · Question #87
Complete the sentence. A gap analysis will enable the architect to do all of the following except _____.
The correct answer is E. identify potential vendors to provide new building blocks. Gap analysis is a TOGAF technique used to compare the Baseline Architecture with the Target Architecture to identify differences - what was intentionally eliminated, what is carried over, what is inadvertently omitted, and what new building blocks are needed. However, identifying
Question
Complete the sentence. A gap analysis will enable the architect to do all of the following except _____.
Options
- Aidentify building blocks that have been inadvertently omitted
- Bidentify building blocks that have been intentionally eliminated
- Cidentify building blocks to be carried over
- Didentify new building blocks that are needed
- Eidentify potential vendors to provide new building blocks
How the community answered
(58 responses)- A2% (1)
- B2% (1)
- C3% (2)
- E93% (54)
Explanation
Gap analysis is a TOGAF technique used to compare the Baseline Architecture with the Target Architecture to identify differences - what was intentionally eliminated, what is carried over, what is inadvertently omitted, and what new building blocks are needed. However, identifying potential vendors to provide new building blocks is not a purpose of gap analysis. Vendor selection is a procurement or sourcing activity that occurs separately (often in Phase E or later). Gap analysis is strictly about architectural completeness and change identification, not market or vendor evaluation.
Topics
Community Discussion
No community discussion yet for this question.