Gap Analysis is a technique used in Phases B, C, D and E.Which one of the following statements best describes the gap analysis technique?

The correct answer is C. It highlights services that are yet to be developed. Gap Analysis is used to identify differences between the Baseline Architecture (current state) and the Target Architecture (desired state). The 'gaps' represent things that are missing, need to be added, changed, or removed. In the context of architecture domains (Business…

Submitted by kavita_s· Apr 18, 2026ADM Guidelines and Techniques

Question

Gap Analysis is a technique used in Phases B, C, D and E.Which one of the following statements best describes the gap analysis technique?

Options

  • AIt highlights areas of stakeholder concern
  • BIt highlights the impacts of change
  • CIt highlights services that are yet to be developed
  • DIt highlights services that are available
  • EIt highlights different viewpoints

How the community answered

(33 responses)
  • B
    6% (2)
  • C
    91% (30)
  • D
    3% (1)

Explanation

Gap Analysis is used to identify differences between the Baseline Architecture (current state) and the Target Architecture (desired state). The 'gaps' represent things that are missing, need to be added, changed, or removed. In the context of architecture domains (Business, Data, Application, Technology), this most accurately means identifying capabilities, components, or services that do not yet exist but need to be created. The technique produces a gap matrix comparing what exists now versus what is needed, which then drives the work packages and roadmap in Migration Planning. It does not primarily highlight stakeholder concerns, change impacts, available services, or viewpoints - those are addressed by other TOGAF techniques.