In Which phase of the TOGAF ADM are Gap Analysis results from earlier phases consolidated?
The correct answer is B. Phase E. Phase E (Opportunities and Solutions) is where the Gap Analysis results produced in Phases B (Business Architecture), C (Information Systems Architecture), and D (Technology Architecture) are consolidated. In Phase E, these gaps are reviewed together to identify candidate…
Question
In Which phase of the TOGAF ADM are Gap Analysis results from earlier phases consolidated?
Options
- APhase D
- BPhase E
- CPhase F
- DPhase G
- EPhase H
How the community answered
(28 responses)- B89% (25)
- C4% (1)
- E7% (2)
Explanation
Phase E (Opportunities and Solutions) is where the Gap Analysis results produced in Phases B (Business Architecture), C (Information Systems Architecture), and D (Technology Architecture) are consolidated. In Phase E, these gaps are reviewed together to identify candidate implementation projects, work packages, and transition architectures. Phase F covers migration planning, Phase G covers implementation governance, and Phase H covers architecture change management - none of which perform the consolidation of gap analysis outputs.