OG0-091 · Question #28

OG0-091 Question #28: Real Exam Question with Answer & Explanation

The correct answer is A: Architecture Contract. In Phase G (Implementation Governance), the Architecture Contract is the formal agreement between the architecture organization (who defines standards and requirements) and the implementation/development organization (who builds the solution). It establishes mutual commitments, d

Submitted by packet_pusher· Apr 18, 2026TOGAF ADM

Question

In Phase G, What document establishes the connection between the architecture organization and the implementation organization?

Options

  • AArchitecture Contract
  • BArchitecture Landscape
  • CArchitecture Roadmap
  • DRequirements Impact Statement
  • ETransition Architecture

Explanation

In Phase G (Implementation Governance), the Architecture Contract is the formal agreement between the architecture organization (who defines standards and requirements) and the implementation/development organization (who builds the solution). It establishes mutual commitments, defines acceptance criteria, and ensures the implementation conforms to the architecture. It is the key governance mechanism linking architects to project delivery teams during implementation.

Topics

#Phase G#Architecture Contract#Implementation Governance#ADM Deliverables

Community Discussion

No community discussion yet for this question.