OG0-091 · Question #6
OG0-091 Question #6: Real Exam Question with Answer & Explanation
The correct answer is D: Request for Architecture Work. A Request for Architecture Work is the document that formally triggers an ADM cycle. It is typically issued by senior management or a sponsoring business unit to the architecture practice, requesting that architecture work be undertaken for a specific business problem or opportun
Question
What document is used to initiate a TOGAF ADM cycle?
Options
- AArchitecture Roadmap
- BStatement of Architecture Work
- CArchitecture Landscape
- DRequest for Architecture Work
- EArchitecture Vision
Explanation
A Request for Architecture Work is the document that formally triggers an ADM cycle. It is typically issued by senior management or a sponsoring business unit to the architecture practice, requesting that architecture work be undertaken for a specific business problem or opportunity. It is the input to the Preliminary Phase and Phase A. The Architecture Vision, Statement of Architecture Work, and Architecture Roadmap are outputs produced during the cycle, not the document that initiates it.
Topics
Community Discussion
No community discussion yet for this question.