What document is used to initiate a TOGAF ADM cycle?

The correct answer is D. Request for Architecture Work. A Request for Architecture Work is the document that formally triggers an ADM cycle. It is typically issued by senior management or a sponsoring business unit to the architecture practice, requesting that architecture work be undertaken for a specific business problem or…

Submitted by zhang_li· Apr 18, 2026TOGAF ADM

Question

What document is used to initiate a TOGAF ADM cycle?

Options

  • AArchitecture Roadmap
  • BStatement of Architecture Work
  • CArchitecture Landscape
  • DRequest for Architecture Work
  • EArchitecture Vision

How the community answered

(23 responses)
  • A
    4% (1)
  • D
    91% (21)
  • E
    4% (1)

Explanation

A Request for Architecture Work is the document that formally triggers an ADM cycle. It is typically issued by senior management or a sponsoring business unit to the architecture practice, requesting that architecture work be undertaken for a specific business problem or opportunity. It is the input to the Preliminary Phase and Phase A. The Architecture Vision, Statement of Architecture Work, and Architecture Roadmap are outputs produced during the cycle, not the document that initiates it.

Topics

#TOGAF ADM#ADM Initiation#Request for Architecture Work#Architecture Process