nerdexam
The_Open_GroupThe_Open_Group

OG0-091 · Question #6

OG0-091 Question #6: Real Exam Question with Answer & Explanation

The correct answer is D: Request for Architecture Work. A Request for Architecture Work is the document that formally triggers an ADM cycle. It is typically issued by senior management or a sponsoring business unit to the architecture practice, requesting that architecture work be undertaken for a specific business problem or opportun

Submitted by zhang_li· Apr 18, 2026TOGAF ADM

Question

What document is used to initiate a TOGAF ADM cycle?

Options

  • AArchitecture Roadmap
  • BStatement of Architecture Work
  • CArchitecture Landscape
  • DRequest for Architecture Work
  • EArchitecture Vision

Explanation

A Request for Architecture Work is the document that formally triggers an ADM cycle. It is typically issued by senior management or a sponsoring business unit to the architecture practice, requesting that architecture work be undertaken for a specific business problem or opportunity. It is the input to the Preliminary Phase and Phase A. The Architecture Vision, Statement of Architecture Work, and Architecture Roadmap are outputs produced during the cycle, not the document that initiates it.

Topics

#TOGAF ADM#ADM Initiation#Request for Architecture Work#Architecture Process

Community Discussion

No community discussion yet for this question.

Full OG0-091 PracticeBrowse All OG0-091 Questions