nerdexam
The_Open_Group

OG0-091 · Question #55

Which one of the following is an objective of the Preliminary Phase of the ADM?

The correct answer is C. To define the framework and methodologies to be used. The Preliminary Phase is concerned with preparation and initiation activities needed before starting an ADM cycle. A key objective is to define the architecture framework and methodologies that will be used, including tailoring TOGAF if needed, establishing governance, and…

Submitted by kevin_r· Apr 18, 2026TOGAF ADM

Question

Which one of the following is an objective of the Preliminary Phase of the ADM?

Options

  • ATo define the Baseline Architecture for this cycle of the ADM
  • BTo define the application systems for the Target Architecture
  • CTo define the framework and methodologies to be used
  • DTo define the relevant stakeholders and their concerns
  • ETo define and prioritise work packages

How the community answered

(19 responses)
  • A
    5% (1)
  • C
    95% (18)

Explanation

The Preliminary Phase is concerned with preparation and initiation activities needed before starting an ADM cycle. A key objective is to define the architecture framework and methodologies that will be used, including tailoring TOGAF if needed, establishing governance, and setting up the Architecture Capability. Defining the Baseline Architecture happens in Phase A/B/C/D; defining application systems targets is Phase C; stakeholder concerns are addressed in Phase A; and work package prioritization is Phase E/F.

Topics

#TOGAF ADM#Preliminary Phase#Architecture Framework#Methodology

Community Discussion

No community discussion yet for this question.

Full OG0-091 Practice