OG0-091 · Question #55
Which one of the following is an objective of the Preliminary Phase of the ADM?
The correct answer is C. To define the framework and methodologies to be used. The Preliminary Phase is concerned with preparation and initiation activities needed before starting an ADM cycle. A key objective is to define the architecture framework and methodologies that will be used, including tailoring TOGAF if needed, establishing governance, and…
Question
Which one of the following is an objective of the Preliminary Phase of the ADM?
Options
- ATo define the Baseline Architecture for this cycle of the ADM
- BTo define the application systems for the Target Architecture
- CTo define the framework and methodologies to be used
- DTo define the relevant stakeholders and their concerns
- ETo define and prioritise work packages
How the community answered
(19 responses)- A5% (1)
- C95% (18)
Explanation
The Preliminary Phase is concerned with preparation and initiation activities needed before starting an ADM cycle. A key objective is to define the architecture framework and methodologies that will be used, including tailoring TOGAF if needed, establishing governance, and setting up the Architecture Capability. Defining the Baseline Architecture happens in Phase A/B/C/D; defining application systems targets is Phase C; stakeholder concerns are addressed in Phase A; and work package prioritization is Phase E/F.
Topics
Community Discussion