OG0-091 · Question #32
OG0-091 Question #32: Real Exam Question with Answer & Explanation
The correct answer is D: Risk is pervasive in all enterprise architecture activity and should be managed in all phases of the. TOGAF explicitly states that risk management is not confined to any single phase. Risk identification, classification, and mitigation are relevant at every stage — from the Preliminary Phase through Architecture Change Management. Risks may include business risks, technology ri
Question
Which of the following statements best describes risk management in the ADM?
Options
- ARisk analysis is best conducted in the Architecture Vision phase so that the risk is eliminated in
- BRisk analysis should be carried out first in the Migration Planning phase
- CRisk analysis is outside the scope of enterprise architecture projects
- DRisk is pervasive in all enterprise architecture activity and should be managed in all phases of the
- EThe only risks that are within the scope of enterprise architecture are technological risks
Explanation
TOGAF explicitly states that risk management is not confined to any single phase. Risk identification, classification, and mitigation are relevant at every stage — from the Preliminary Phase through Architecture Change Management. Risks may include business risks, technology risks, transition risks, and more. TOGAF recommends that risks be identified and assessed initially in the Architecture Vision phase and then continuously re-evaluated as the ADM progresses. Limiting risk to a single phase (as the distractors suggest) would leave unaddressed risks in other phases, which is contrary to TOGAF guidance.
Topics
Community Discussion
No community discussion yet for this question.