OG0-091 · Question #268
In which ADM phase does the value and change management process determine the circumstances under which the Architecture Development Cycle will be initiated to develop a new architecture?
The correct answer is A. Phase H. Phase H - Architecture Change Management - is the final phase of the TOGAF ADM cycle and is explicitly responsible for managing changes to the architecture in a controlled way. It establishes and operates a value management process that monitors for business or technology…
Question
In which ADM phase does the value and change management process determine the circumstances under which the Architecture Development Cycle will be initiated to develop a new architecture?
Options
- APhase H
- BPhase F
- CPhase E
- DPreliminary Phase
- EPhase G
How the community answered
(34 responses)- A88% (30)
- B3% (1)
- C3% (1)
- D6% (2)
Explanation
Phase H - Architecture Change Management - is the final phase of the TOGAF ADM cycle and is explicitly responsible for managing changes to the architecture in a controlled way. It establishes and operates a value management process that monitors for business or technology changes, assesses their impact, and determines whether those changes warrant initiating a new ADM cycle. This is what triggers the loop back to the Preliminary Phase or Phase A.
Topics
Community Discussion
No community discussion yet for this question.