OG0-091 · Question #261
In which ADM Phase is the focus the creation of an Implementation and Migration Plan in co- operation with the portfolio and project managers?
The correct answer is B. Phase F. Phase F (Migration Planning) is specifically focused on producing the Implementation and Migration Plan, which details the sequence of transition architectures and projects needed to move from the Baseline to the Target Architecture. This phase involves close collaboration with…
Question
In which ADM Phase is the focus the creation of an Implementation and Migration Plan in co- operation with the portfolio and project managers?
Options
- APhase A
- BPhase F
- CPhase D
- DPhase G
- EPhase E
How the community answered
(43 responses)- B91% (39)
- C5% (2)
- D2% (1)
- E2% (1)
Explanation
Phase F (Migration Planning) is specifically focused on producing the Implementation and Migration Plan, which details the sequence of transition architectures and projects needed to move from the Baseline to the Target Architecture. This phase involves close collaboration with portfolio managers and project managers to ensure that projects are prioritized, resourced, and sequenced appropriately. Phase E (Opportunities and Solutions) identifies the projects; Phase F plans how to execute them.