What is an objective of the ADM Preliminary Phase?
The correct answer is C. To select and implement tools to support the Architecture Capability. The Preliminary Phase is about setting up the architecture practice - this includes selecting and deploying architecture tools (such as modeling tools and repositories) to support the Architecture Capability. The other options belong to different phases: creating the…
Question
What is an objective of the ADM Preliminary Phase?
Options
- ATo create the initial version of the Architecture Roadmap
- BTo develop a vision of the business value to be delivered by the proposed enterprise architecture
- CTo select and implement tools to support the Architecture Capability
- DTo obtain approval for the Statement of Architecture Work
- ETo document the baseline architecture
How the community answered
(62 responses)- A2% (1)
- B3% (2)
- C94% (58)
- D2% (1)
Explanation
The Preliminary Phase is about setting up the architecture practice - this includes selecting and deploying architecture tools (such as modeling tools and repositories) to support the Architecture Capability. The other options belong to different phases: creating the Architecture Roadmap is Phase E, developing the business value vision is Phase A, obtaining approval for the Statement of Architecture Work is Phase A, and documenting baseline architecture occurs in Phases B through D.