nerdexam
The_Open_Group

OG0-091 · Question #238

Which one of the following is an objective of the Preliminary Phase of the ADM?

The correct answer is B. To define the architecture principles. The Preliminary Phase of the TOGAF ADM is concerned with preparing the organization for an architecture project. One of its key objectives is to define the architecture principles that will guide all subsequent ADM cycle work. The other choices belong to different phases…

Submitted by diego_uy· Apr 18, 2026TOGAF ADM

Question

Which one of the following is an objective of the Preliminary Phase of the ADM?

Options

  • ATo define, scope and prioritize architecture tasks
  • BTo define the architecture principles
  • CTo develop a Target Business Architecture
  • DTo obtain management commitment for this cycle of the ADM
  • ETo prioritize work packages

How the community answered

(57 responses)
  • A
    7% (4)
  • B
    86% (49)
  • C
    4% (2)
  • D
    2% (1)
  • E
    2% (1)

Explanation

The Preliminary Phase of the TOGAF ADM is concerned with preparing the organization for an architecture project. One of its key objectives is to define the architecture principles that will guide all subsequent ADM cycle work. The other choices belong to different phases: defining, scoping, and prioritizing architecture tasks is part of Phase A (Architecture Vision); developing a Target Business Architecture is Phase B; obtaining management commitment for an ADM cycle is Phase A; prioritizing work packages occurs in Phase E (Opportunities and Solutions).

Topics

#Preliminary Phase#ADM#Architecture Principles#Phase Objectives

Community Discussion

No community discussion yet for this question.

Full OG0-091 Practice