According to TOGAF, who usually initiates a Request for Architecture Work?

The correct answer is E. The sponsoring organization. According to TOGAF, a Request for Architecture Work is usually initiated by the sponsoring organization - typically the board of directors, senior management, or business leadership - to commission architecture work. This document is sent to the architecture organization to…

Submitted by renata2k· Apr 18, 2026TOGAF ADM

Question

According to TOGAF, who usually initiates a Request for Architecture Work?

Options

  • AThe architecture organization
  • BThe CIO/CTO
  • CThe corporate governance board
  • DThe senior management
  • EThe sponsoring organization

How the community answered

(48 responses)
  • A
    6% (3)
  • B
    2% (1)
  • C
    4% (2)
  • E
    88% (42)

Explanation

According to TOGAF, a Request for Architecture Work is usually initiated by the sponsoring organization - typically the board of directors, senior management, or business leadership - to commission architecture work. This document is sent to the architecture organization to trigger the start of an ADM cycle. While the CIO/CTO, corporate governance, or senior management may be involved, TOGAF specifically identifies the sponsoring organization as the initiator, since they are the entity commissioning and funding the architecture effort.