OG0-091 · Question #216
OG0-091 Question #216: Real Exam Question with Answer & Explanation
The correct answer is D: To highlight shortfalls between the baseline and target architectures. Gap Analysis is a technique used throughout Phases B, C, and D of the ADM to identify the differences (gaps) between the Baseline Architecture (current state) and the Target Architecture (desired future state). These gaps drive the work required to transition from the current to
Question
Which of the following best describes a purpose of the Gap Analysis technique?
Options
- ATo catch errors in a project architecture early
- BTo guide decision making throughout the enterprise
- CTo help identify and understand business requirements
- DTo highlight shortfalls between the baseline and target architectures
- ETo mitigate risk when implementing an architecture project
Explanation
Gap Analysis is a technique used throughout Phases B, C, and D of the ADM to identify the differences (gaps) between the Baseline Architecture (current state) and the Target Architecture (desired future state). These gaps drive the work required to transition from the current to the future state. It is not primarily about catching errors (A), guiding decision-making broadly (B), identifying business requirements (C), or mitigating risk (E) — those are purposes of other techniques.