nerdexam
The_Open_Group

OG0-091 · Question #159

Which of the following statements best describes the Requirements Management process?

The correct answer is D. It is used to manage architecture requirements throughout the ADM cycle. Requirements Management is the central, continuous process in the TOGAF ADM that runs throughout all phases. Its role is to ensure that architecture requirements are identified, stored, and fed into and out of every ADM phase as they evolve. It does not generate requirements…

Submitted by renata2k· Apr 18, 2026TOGAF ADM

Question

Which of the following statements best describes the Requirements Management process?

Options

  • AIt is used to develop requirements for Transition Architectures that deliver business value
  • BIt is used to dispose of, address and prioritize architecture requirements
  • CIt is used to establish requirements for Phase A
  • DIt is used to manage architecture requirements throughout the ADM cycle
  • EIt is used to review business requirements

How the community answered

(55 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    2% (1)
  • D
    85% (47)
  • E
    7% (4)

Explanation

Requirements Management is the central, continuous process in the TOGAF ADM that runs throughout all phases. Its role is to ensure that architecture requirements are identified, stored, and fed into and out of every ADM phase as they evolve. It does not generate requirements for a single phase (A or C), nor does it dispose of or prioritize requirements (B-that is done within individual phases), nor is it limited to reviewing business requirements (E). Its scope is the entire ADM lifecycle, acting as the hub for requirements flow.

Topics

#Requirements Management#TOGAF ADM#ADM Cycle#Architecture Requirements

Community Discussion

No community discussion yet for this question.

Full OG0-091 Practice