OG0-091 · Question #108
Complete the sentence. During the implementation of an architecture, if the original Architecture Definition and requirements are not suitable, a ____ may be submitted to initiate further…
The correct answer is B. Change Request. If during implementation it becomes clear that the original Architecture Definition Document or requirements are no longer suitable - due to changed circumstances, new constraints, or discovered gaps - a Change Request is formally submitted. This triggers Phase H (Architecture…
Question
Complete the sentence. During the implementation of an architecture, if the original Architecture Definition and requirements are not suitable, a ____ may be submitted to initiate further architecture work.
Options
- ACapability Assessment
- BChange Request
- CRequirements Impact Analysis
- DStatement of Architecture Work
How the community answered
(22 responses)- A5% (1)
- B91% (20)
- D5% (1)
Explanation
If during implementation it becomes clear that the original Architecture Definition Document or requirements are no longer suitable - due to changed circumstances, new constraints, or discovered gaps - a Change Request is formally submitted. This triggers Phase H (Architecture Change Management), which evaluates the impact and determines whether to initiate a new ADM cycle. A Change Request is the formal mechanism for surfacing the need for architecture rework.
Topics
Community Discussion
No community discussion yet for this question.