Which one of the following statements about the Requirements Management phase is true?
The correct answer is C. The phase manages the flow of requirements, storing them, and feeding them in and out of the. The Requirements Management phase is a continuous, central phase that runs throughout the entire ADM cycle. Its role is to store requirements and manage the flow of requirements into and out of all other ADM phases - it does not itself generate, prioritize, resolve, or defer requ
Question
Which one of the following statements about the Requirements Management phase is true?
Options
- AAll requirements fed into the phase are prioritized, and those of low priority are deferred until the
- BThe phase generates the requirements for a given ADM cycle using the Business Scenario
- CThe phase manages the flow of requirements, storing them, and feeding them in and out of the
- DThe phase operates like a waiting room, and all requirements fed in to the phase must be
- EThe phase resolves the requirements that are fed into it from the other ADM phases
How the community answered
(24 responses)- A4% (1)
- C96% (23)
Explanation
The Requirements Management phase is a continuous, central phase that runs throughout the entire ADM cycle. Its role is to store requirements and manage the flow of requirements into and out of all other ADM phases - it does not itself generate, prioritize, resolve, or defer requirements. Those activities happen within the individual ADM phases. Think of it as a dynamic repository and routing mechanism, not a decision-making phase.