NS0-504 · Question #321
NS0-504 Question #321: Real Exam Question with Answer & Explanation
The correct answer is D. Finalize switch zone configurations. See the full explanation below for the reasoning.
Question
iSCSI and FC SAN deployments share requirements for these planning steps with one exception. Which task is NOT required for both types of deployments?
Options
- AReview implementation flowchart with customer - assign tasks
- BVerify logistics plan for staging and installation of equipment
- CValidate equipment move path to installation location (doorway clearances, floor loading
- DFinalize switch zone configurations
- EVerify Ethernet cabling plan and availability of cable supports