Which three tasks should be completed as part of the site preparation for install? (Choose three.)
The correct answer is B. verify equipment move path D. verify power drops in the equipment location E. make contact with data center personnel. See the full explanation below for the reasoning.
Question
Which three tasks should be completed as part of the site preparation for install? (Choose three.)
Options
- Aplan zoning configuration
- Bverify equipment move path
- Cdetermine aggregate layout
- Dverify power drops in the equipment location
- Emake contact with data center personnel
How the community answered
(30 responses)- A20% (6)
- B70% (21)
- C10% (3)