NCSE-CORE · Question #139
A customer plans to migrate a business critical,highly tranactional SQL Server database to Nutanix Currently the databases is running on a physical server with 256GB of RAM and 12CPU cores at > 80%…
The correct answer is D. Intel E5 2667v4 ( 8 cores each @ 3.2GHZ, 16 Cores total). See the full explanation below for the reasoning.
Question
A customer plans to migrate a business critical,highly tranactional SQL Server database to Nutanix Currently the databases is running on a physical server with 256GB of RAM and 12CPU cores at > 80% utilization To run the VM on a single NUMA node, which processor configuration should the SE recommend for this workload?
Options
- AIntel E5 2680v4 (14 cores each @ 2.4GHZ, 28 Cores total)
- BIntel E5 2620v4 ( 8 cores each @ 2.1GHZ, 16 Cores total)
- CIntel E5 2643v4 ( 6 cores each @ 3.4GHZ, 12 Cores total)
- DIntel E5 2667v4 ( 8 cores each @ 3.2GHZ, 16 Cores total)
How the community answered
(50 responses)- A16% (8)
- B8% (4)
- C4% (2)
- D72% (36)