NCA-5.15 · Question #15
An administrator has planned a RAM upgrade on a 3-node Nutanix cluster. Which step should be performed first for a non-disruptive memory upgrade?
The correct answer is B. RunNCC. Before performing any maintenance on a Nutanix cluster - especially hardware changes - the administrator should first run NCC (Nutanix Cluster Check). NCC performs a comprehensive health check of the cluster (hardware, software, services, replication) to confirm the cluster is…
Question
An administrator has planned a RAM upgrade on a 3-node Nutanix cluster. Which step should be performed first for a non-disruptive memory upgrade?
Options
- AStop one CVM at time
- BRunNCC
- CPower off one host at time
- DLive Migrate VMs
How the community answered
(19 responses)- A11% (2)
- B84% (16)
- C5% (1)
Explanation
Before performing any maintenance on a Nutanix cluster - especially hardware changes - the administrator should first run NCC (Nutanix Cluster Check). NCC performs a comprehensive health check of the cluster (hardware, software, services, replication) to confirm the cluster is in a healthy state and safe to proceed. Performing maintenance on a cluster that already has a degraded component could result in data loss or an outage. Live migrating VMs (D) and stopping CVMs (A) are steps that come later in the process. Powering off a host (C) before confirming cluster health is risky on a 3-node cluster where RF2 tolerance is minimal.