N10-005 · Question #688
The day network administrator is having problems on the network and realizes that the night administrator implemented a new device that is causing broadcast traffic. Which of the following should be…
The correct answer is D. Change management. Change management is a formal process requiring all network changes to be documented, approved, and communicated before implementation. If a proper change management process had been in place, the night administrator's new device would have been logged and communicated to the…
Question
The day network administrator is having problems on the network and realizes that the night administrator implemented a new device that is causing broadcast traffic. Which of the following should be implemented to avoid miscommunication between the administrators?
Options
- AAsset management
- BSystem baselines
- CSystem logging
- DChange management
How the community answered
(17 responses)- C6% (1)
- D94% (16)
Explanation
Change management is a formal process requiring all network changes to be documented, approved, and communicated before implementation. If a proper change management process had been in place, the night administrator's new device would have been logged and communicated to the day team, preventing confusion. Asset management tracks what devices exist, system baselines document normal configurations, and system logging records events - none of these specifically prevent the communication gap that change management addresses.