N10-005 · Question #24
A technician decides to upgrade a router before leaving for vacation. While away, users begin to report slow performance. Which of the following practices allows other technicians to quickly return…
The correct answer is A. Change management. As soon as technician found a problem he generates a change management request to make changes to fast up the speed of router.
Network operations
Question
A technician decides to upgrade a router before leaving for vacation. While away, users begin to report slow performance. Which of the following practices allows other technicians to quickly return the network to normal speeds?
Options
- AChange management
- BBaselines
- CAsset management
- DCable management
How the community answered
(27 responses)- A93% (25)
- B4% (1)
- D4% (1)
Explanation
As soon as technician found a problem he generates a change management request to make changes to fast up the speed of router.
Topics
#change management#rollback procedure#network operations