EXIN
MOFF · Question #91
In which step of the Risk Management Discipline are risks monitored for changes in the risk's condition, consequence, probability, and impact?
The correct answer is D. Track and Report. See the full explanation below for the reasoning.
Question
In which step of the Risk Management Discipline are risks monitored for changes in the risk's condition, consequence, probability, and impact?
Options
- AIdentify
- BControl
- CPlan and Schedule
- DTrack and Report
How the community answered
(41 responses)- A15% (6)
- B5% (2)
- C7% (3)
- D73% (30)
Community Discussion