MOFF · Question #34
Which is not a goal of the Project Planning SMF?
The correct answer is A. Approve all changes to the project. See the full explanation below for the reasoning.
Question
Which is not a goal of the Project Planning SMF?
Options
- AApprove all changes to the project
- BDeliver a clearly scoped project plan
- CDeliver a functional specification
- DProduce a master project schedule
How the community answered
(50 responses)- A78% (39)
- B6% (3)
- C4% (2)
- D12% (6)