MOFF · Question #34

Which is not a goal of the Project Planning SMF?

The correct answer is A. Approve all changes to the project. See the full explanation below for the reasoning.

Question

Which is not a goal of the Project Planning SMF?

Options

  • AApprove all changes to the project
  • BDeliver a clearly scoped project plan
  • CDeliver a functional specification
  • DProduce a master project schedule

How the community answered

(50 responses)
  • A
    78% (39)
  • B
    6% (3)
  • C
    4% (2)
  • D
    12% (6)