EXIN
MOFF · Question #29
Which phase transfers a successfully deployed new service to the Operate phase?
The correct answer is B. Deliver. See the full explanation below for the reasoning.
Question
Which phase transfers a successfully deployed new service to the Operate phase?
Options
- ABuild
- BDeliver
- CDeploy
- DPlan
How the community answered
(32 responses)- A9% (3)
- B81% (26)
- C6% (2)
- D3% (1)
Community Discussion