EXIN
MOFF · Question #17
When is the milestone review report signed off in the Project Planning SMF?
The correct answer is B. After approving the functional specification, master project plan and master schedule. See the full explanation below for the reasoning.
Question
When is the milestone review report signed off in the Project Planning SMF?
Options
- AAfter approving the request for change
- BAfter approving the functional specification, master project plan and master schedule
- CAfter it has been transferred to IT Operations
- DBefore approving the functional specification, master project plan and master schedule
How the community answered
(37 responses)- A16% (6)
- B73% (27)
- C3% (1)
- D8% (3)
Community Discussion
No community discussion yet for this question.