Question

When is the milestone review report signed off in the Project Planning SMF?

Options

  • AAfter approving the request for change
  • BAfter approving the functional specification, master project plan and master schedule
  • CAfter it has been transferred to IT Operations
  • DBefore approving the functional specification, master project plan and master schedule