Microsoft
MB6-898 · Question #42
MB6-898 Question #42: Real Exam Question with Answer & Explanation
The correct answer is B. Set up a new leave and absence plan called "Paid holiday" with a start date of January 1 next. https://docs.microsoft.com/en-us/dynamics365/unified-operations/fin-and- ops/hr/localizations/noam-usa-benefit-accrual-plan-tasks
Question
Your company makes a change in their paid holiday leave and absence plan. Any employee who works six years or more for the company will receive two extra paid holiday days starting on January 1 of next year. What should you do to make this change available?
Options
- ASet up a new leave and absence plan called "Paid holiday" with a start date of January 1 next
- BSet up a new leave and absence plan called "Paid holiday" with a start date of January 1 next
- CAdjust the existing paid holiday leave and absence plan to include the accrual schedule for
- DAdjust the existing paid holiday leave and absence plan to include the accrual schedule for
Explanation
https://docs.microsoft.com/en-us/dynamics365/unified-operations/fin-and- ops/hr/localizations/noam-usa-benefit-accrual-plan-tasks
Community Discussion
No community discussion yet for this question.