A technician completes a service order request at a customer site but uses a different component than is specified on the service bill of materials (BOM). You need to record the change in Microsoft…

The correct answer is D. Replace the component in the BOM Designer. See the full explanation below for the reasoning.

Question

A technician completes a service order request at a customer site but uses a different component than is specified on the service bill of materials (BOM). You need to record the change in Microsoft Dynamics AX 2012. What should you do?

Options

  • AAdd an activity line for the new component in the service order.
  • BAdd the component in the BOM Designer.
  • CReplace the activity lines in the service order.
  • DReplace the component in the BOM Designer.

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    11% (4)
  • D
    81% (30)