MB6-889 · Question #10

A service order line in Microsoft Dynamics AX 2012 has a transaction type of Hour and a quantity of 5 hours. The start date and end date are June 1. Service technicians work 8-hour shifts, every…

The correct answer is A. June 3. See the full explanation below for the reasoning.

Question

A service order line in Microsoft Dynamics AX 2012 has a transaction type of Hour and a quantity of 5 hours. The start date and end date are June 1. Service technicians work 8-hour shifts, every day. In the dispatch board, you create another activity of the same type with a quantity of 12 hours. What is the end date of the new activity?

Options

  • AJune 3
  • BJune 2
  • CJune 4
  • DJune 1

How the community answered

(19 responses)
  • A
    74% (14)
  • B
    5% (1)
  • C
    16% (3)
  • D
    5% (1)