Question
A service order line in Microsoft Dynamics AX 2012 has a transaction type of Hour and a quantity of 5 hours. The start date and end date are June 1. Service technicians work 8-hour shifts, every day. In the dispatch board, you create another activity of the same type with a quantity of 12 hours. What is the end date of the new activity?
Options
- AJune 3
- BJune 2
- CJune 4
- DJune 1
How the community answered
(19 responses)- A74% (14)
- B5% (1)
- C16% (3)
- D5% (1)