Microsoft
MB6-885 · Question #62
What are the two stages of a budget register? (Each correct answer presents part of the solutions. Choose two.)
The correct answer is A. Draft budget revisions with a status of Draft E. Completed budget revisions with a status of Completed. See the full explanation below for the reasoning.
Question
What are the two stages of a budget register? (Each correct answer presents part of the solutions. Choose two.)
Options
- ADraft budget revisions with a status of Draft
- BPosted budget revisions with a status of Posted
- COn-hold budget revisions with a status of Hold
- DRelease-ready budget revisions with a status of Release Now
- ECompleted budget revisions with a status of Completed
How the community answered
(46 responses)- A74% (34)
- B9% (4)
- C2% (1)
- D15% (7)
Community Discussion
No community discussion yet for this question.