Question
You need to configure budget control to issue a notification when the amount of budget funds spent reaches 90% of the expenses. In Microsoft Dynamics AX 2012, which option should you set to trigger the notification?
Options
- Abudget control interval
- Bbudget threshold
- Cbudget dimensions
- Dbudget cycle time span
How the community answered
(40 responses)- A8% (3)
- B80% (32)
- C3% (1)
- D10% (4)