Question

You need to configure budget control to issue a notification when the amount of budget funds spent reaches 90% of the expenses. In Microsoft Dynamics AX 2012, which option should you set to trigger the notification?

Options

  • Abudget control interval
  • Bbudget threshold
  • Cbudget dimensions
  • Dbudget cycle time span

How the community answered

(40 responses)
  • A
    8% (3)
  • B
    80% (32)
  • C
    3% (1)
  • D
    10% (4)