Microsoft
MB6-885 · Question #57
In Microsoft Dynamics AX 2012, you need to configure budget control on an apportionment budget that will fund over several periods. You need to ensure that only a specific amount of money is…
The correct answer is C. Use only apportioned amount only. See the full explanation below for the reasoning.
Question
In Microsoft Dynamics AX 2012, you need to configure budget control on an apportionment budget that will fund over several periods. You need to ensure that only a specific amount of money is released for expenditures until the original budget is finalized. Which apportionment option or options should you select?
Options
- AUse only apportioned amount and Include carry-forward amounts
- BInclude carry-forward amounts and Amounts to Sum-original budget and preliminary budget
- CUse only apportioned amount only
- DUse only apportioned amount and Amounts to Sum - preliminary budget and budget revisions
How the community answered
(26 responses)- A15% (4)
- B4% (1)
- C73% (19)
- D8% (2)
Community Discussion
No community discussion yet for this question.