For reporting purposes, you need to present provisional budgets and apportionment budgets separately in Microsoft Dynamics AX 2012. Which report should you use?

The correct answer is D. Budget details. See the full explanation below for the reasoning.

Question

For reporting purposes, you need to present provisional budgets and apportionment budgets separately in Microsoft Dynamics AX 2012. Which report should you use?

Options

  • AActual vs. budget
  • BBudget control activity by project
  • CBudget control account detail history
  • DBudget details

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    13% (4)
  • C
    3% (1)
  • D
    80% (24)