In Microsoft Dynamics AX 2012, you need to reverse a provisional budget and update the budget register with an original budget. Which three attributes must the original budget and the provisional…
The correct answer is C. Budget Code D. Period E. Budget Cycle. See the full explanation below for the reasoning.
Question
In Microsoft Dynamics AX 2012, you need to reverse a provisional budget and update the budget register with an original budget. Which three attributes must the original budget and the provisional budget share? (Each correct answer presents a partial solution. Choose three.)
Options
- ABudget Model
- BDimension Values
- CBudget Code
- DPeriod
- EBudget Cycle
How the community answered
(69 responses)- A13% (9)
- B7% (5)
- C80% (55)