Microsoft
MB6-885 · Question #17
You plan to create a project budget in Microsoft Dynamics AX 2012. The project budget will be based on the budget for costs and revenue of a subproject. Which of the following properties can you use…
The correct answer is A. Project budget ID C. Budget source. See the full explanation below for the reasoning.
Question
You plan to create a project budget in Microsoft Dynamics AX 2012. The project budget will be based on the budget for costs and revenue of a subproject. Which of the following properties can you use to associate the subproject? (Each correct answer presents a complete solution. Choose two.)
Options
- AProject budget ID
- BTransaction type for cost and revenue
- CBudget source
- DProject for cost and revenue
How the community answered
(43 responses)- A86% (37)
- B9% (4)
- D5% (2)
Community Discussion
No community discussion yet for this question.