MB6-885 · Question #14
You are revising an original budget by using the Project budget form in Microsoft Dynamics AX 2012. You need to associate the original budget to the revision. By which field should you associate the…
The correct answer is B. Revision ID. See the full explanation below for the reasoning.
Question
You are revising an original budget by using the Project budget form in Microsoft Dynamics AX 2012. You need to associate the original budget to the revision. By which field should you associate the original and revised budgets?
Options
- ACategory
- BRevision ID
- CRevision Date
- DBudget Source
How the community answered
(48 responses)- A4% (2)
- B71% (34)
- C17% (8)
- D8% (4)