nerdexam
Microsoft

MB6-884 · Question #79

Which cost category of a work cell is considered in costing for Lean manufacturing in Microsoft Dynamics AX 2012?

The correct answer is D. run time. See the full explanation below for the reasoning.

Question

Which cost category of a work cell is considered in costing for Lean manufacturing in Microsoft Dynamics AX 2012?

Options

  • Asetup
  • Bquantity
  • Cdirect outsourcing
  • Drun time

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    9% (2)
  • C
    4% (1)
  • D
    83% (19)

Community Discussion

No community discussion yet for this question.